Urgent changes in ChaRM

Hi,

I have read Dolores's blog and found out (chapter #15) and found out that urgent changes that have been imported to QA will be imported to PROD with the whole project even though these are still in testing:

http://scn.sap.com/people/dolores.correa/blog/2009/07/22/change-request-management-scenario-usual-questions-and-known-errors

Does anyone has a solution to this "normal" behavior? Maybe even with development?

I don't want to create a project/ maintenance cycle for urgent changes only.

Thank you,

Adi

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Jul 31, 2012 at 10:40 AM

    Hi Adi,

    this is solvable starting SP5 via 'Status driven Import' where you can define for transaction types at which status in which system will be transported,

    best regards,

    Michael

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 31, 2012 at 09:50 AM

    Hi,

    Create the Mainatance project and use the project  for both urgent and Normal change

    Plz check the below demo

    https://websmp204.sap-ag.de/~sapidb/011000358700000478022011E/index.htm - Rfc

    https://websmp204.sap-ag.de/~sapidb/011000358700000478072011E/index.htm - NC

    https://websmp104.sap-ag.de/~sapidb/011000358700000478212011E/index.htm - UC

    Rg,

    Karthik

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Adi,

      Not able to stop the TR movement while you importing the TR in PRD.

      Because it take all the TR in project cycle and start importing.

      So if you have TR in urgent and waiting for testing or approval, but added to PRD buffer after TR import in QAS.

      After Normal chaneg TR scedule , all TR in project cycle start import.(urgent change TR also).

      As i know, try to delete the TR in Stms queue and import the normal change TR . after import add the urgent changeTR in buffer.

      other wise, create the new project for urgent and normal change.

      Rg,

      Karthik