PM PLAN SCHEDULING CONFIRMATION

Dear Experts

In iw38 we are doing the overall confirmation thing is that my intention is i want to confirm actual start and finished date is 01.07.2012 but system taking the actual start date is 01.07.2012 and finish date is 31.07.2012.could any one plz help me.

Regds

Ganesh

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Jul 31, 2012 at 07:37 AM

    Hi,

    If there are multiple confirmations for an operation, then system considers earliest date/time and latest date/time as actual start date/time and actual finish date/time.

    In your case there may be one more confirmation done earlier with work end date as 31.07.2012. Hence you are getting this date as actual finish date. Pls check and revert.

    rgds,

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.