hi all,

i am trying to configure split valuation,but i want to clear one thing.when we ceated material master for two valuation type then

we have to enter two different valuation class for two valuation type or one valuation class for both valuation typoe can solve our purpose?

regards

sumit

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • Best Answer
    Jul 28, 2012 at 11:29 AM

    if you are creating 2 valuation types for a material code then you have to run MM01 , 3 times..

    1. you create material with valuation category ( this step tells SAP that material is split valuated)
    2. you create additional accounting view for 1st valuation type
    3. you create additional accounting view for 2st valuation type