Basic date in produciton order is changing when get released

Team,

We are facing some difficulties in production order releasing, when releasing the PO, the basic end date is getting changed, may i know why is it happening?

EG: basis start date is 13.01.2017 when i released the PO , it automatically moved to 02.01.2017..

thanks to hep

Add comment
10|10000 characters needed characters exceeded

  • Former Member

    Hi Venkat,

    Below the details in OPU3, let me know what settings should i dot to control the default changes in PO date

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Jan 02, 2017 at 10:57 AM

    Dear Vijesh,

    Due to automatic scheduling while releasing the Production order dates getting change.
    please check the configuration settings of " Specify scheduling parameters"

    ADJUST SCHEDULING & SCHEDULING CONTROL FOR DETAILED SCHEDULING.

    Best Regards

    Venkat

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Venkat,

      Is it possible to provide me the T-code or path to configure the above settings?

      Thanks,

      Vijesh

  • avatar image
    Former Member
    Jan 03, 2017 at 10:29 AM

    Hi Vijesh,

    T-Code is OPU3 for production order.

    Path of SPRO=>PRODUCTION=>Shop floor Control=>Operations=>Scheduling=> Define scheduling parameters for Production order

    Best Regards

    Venkat