on 07-25-2012 2:16 PM
Hello experts,
I need your help in finding how to: make activity allocation from Order to Order?
The t.code I generally use for activity allocation from order to cost center (KB21N) doesn't support this variant.
Is it possible at all?
Thank you in advance.
Bilya
Hi,
try a workaround, from sender order to dummy costcenter (with -sign and the correct activity rate for the activity type) and from dummy costcenter to the receiver order.
BR Christian