PR > Contract > PO but PR was not copied in PO

Hi,

I have a problem

When I create contract with reference to PR and then create PO with reference to contract in t-code ME21N

I have found that PR no and PR item no was not copied in ME21N but I see contract no and contract item no was adopted correctly in ME21N

There're something to do in config or this is just a standard in SAP because if it doesn't copy PR and PR item no in ME21N, it will show PR in MD04 thus MRP will incorrect because stock will double.

Please recommend

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Jul 25, 2012 at 04:48 AM

    It is SAP Standard, When PO created w.r.t. Contract PR No. will not come

    Add a comment
    10|10000 characters needed characters exceeded

    • i am not asking you to create PR with reference to contract , i am telling you process in which contract is assigned as source to PR.

      Yes you are right , if a source is assigned to PR it will become a firmed PR and MRP will not delete it. So its solution is simple assign source only after you are sure you are going to purchase against it.

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.