I've approx 1800 service po's which are released and then partially received via service entry sheet. Now the question is how to mark as complete those po's while those are released.
In PO Line item, Tick the Check box for "Delivery Completed" in Delivery Tab
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
For Problem No 1: If you have release indicator "Cannot be changed" then you have to unrelease PO and do necessary corrections or If you have release indicator "Changeable" then you can do changes in PO even after release.
For Problem No 2: Use t-code MASS select BUS2012 Purchase Orders field Delivery completed Indicator MASSEKPO- ELIKZ. Execute your Purchase orders & update this field.