PIR is not getting consumed in strategy 10

Hello ,

In Planning Strategy 10, when dispatching a material with reference to a Sale order , the PIR is not getting consumed and is remaining as same. I have checked in SPRO configurations as upto my knowledge. Kindly provide the mandatory things to be maintained and Kindly solve this query.

J.Balakrishnan

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    Posted on Jul 20, 2012 at 01:37 PM

    Dear,

    If you want the system to reduce planned independent requirements when it makes withdrawals for sales orders, you must maintain the appropriate consumption period in material master MRP 3 view. In strategy 10 PIR will get consimed after goods issue against delivery. Please refer this link,

    http://scn.sap.com/message/6019930#6019930

    Regards,

    R.Brahmankar

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.