PR/PO commitment not generating

Hi,

Commitment is active in controlling area.

budget tolerance is maintained for ++.

AVAC is active.

When i raise pr from project by releasing the activity, no pr commitment gets generated. Even PO commmitment is not getting generated.

I check avac analysis.

PR value entry is coming in red as:

COSP 2012 01 0000300040 KPPE D INR 10.778,80 INR B

here B refers to Plan Costing Single Position.

Kindly help me resolve this issue.

Thanks,

Harsh.

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

6 Answers

  • Best Answer
    avatar image
    Former Member
    Jul 20, 2012 at 09:13 AM

    Hi,

    I found the problem source. Actually wrong g/l is assigned to the material; it was P/L nature.

    I asked FI to put correct g/l of balance sheet nature in material.

    Now everything is working fine.

    Thanks for all you inputs.

    Regards,

    Harsh.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 19, 2012 at 08:17 AM

    Just a guess, check if the cost element that reports the commitment is suppressed. You can take help of your FICO consultant.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Check whether the suppress indicator is ticked for the cost element. Not sure, but you can check this in the cost element maintenance transaction. Take help from your FICO guys.

  • avatar image
    Former Member
    Jul 19, 2012 at 12:48 PM

    Hi

    Can you check whether cost element is created for that GL Account or not?

    For checking the commitments you also try it posting one FI entry (if it is test client).

    Regards

    Rao

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 20, 2012 at 08:46 AM

    Hello Harsh,

    I think the PR commitment is suppressed in your system. It should update the commitment COOI and COSP table. Please check if you activate the commitment in transaction OKKP. Also please verify all the criteria listed in SAP note 47992 are fulfilled.

    Regards, Gordon

    Add comment
    10|10000 characters needed characters exceeded

  • Jul 20, 2012 at 09:21 AM

    hello harsh,

    check t-code opsc . i think there you have tick planning indicator. if it is so then the cost will book on WBS level not on network level. due to this cost on commitment in not come.

    and do one thing more run t-coe cjen it will uodated the ps info datastructure.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 19, 2013 at 12:29 PM

    Hello,

    see SAP notes 955107 and 1227760.

    Regards