on 07-17-2012 5:12 PM
Hi Experts,
I am trying to do the collective confirmation through IW44, while doing so, it's giving me error message that dates are in future, when i am trying to change the Execution finish date, it's not allowing me to do that. It is copying the date from basic start date and basic finish date of order. This order have status PCNF as it has confirmed through IW41, but not final confirmation. While doing confirmation from IW41, the system is showing the same error as dates are in future, but there it is allowing me to change the date and then to do confirmation. Why is it not allowing to change the same in IW44...
Regards
Hi,
OIZD is for task list usage..
does anyone have answer for my query on confirmation..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I checked, does not found any clue. My question is why the transaction is not allowing to change the end of execution date in IW44,it is taking the latest finish date from the operation date tab, but in IW41 it allows me to change the work finish date. In both case t gives the error for future date, but in IW41 it can be changed as said and confirmation can be done.
Regards
In OIZD, check for the field selection under PM: Confirmation - list and detail for AFRUD-IEDD
Also check the configuration under Control Parameters for Completion Confirmation about Dates in Future.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.