Can i have a check budget/commitment  on documnet type.

clinet wants on certain PR its hould not check the Commitmnet/Budget

we are only using PS no FMor IM

Rgds

John

Accepted Solutions (1)

Accepted Solutions (1)

former_member203098
Active Contributor
0 Kudos

As pranav said in standard system don't have budget check on document types. So with document type ask client for seperate G\L,which we can exclude from budget availability check.

regards,

former_member604117
Participant
0 Kudos

is there any turn arround solution

if you people are sure that document type no chekc is there

former_member203098
Active Contributor
0 Kudos

create separate G/L and exclude from budget availability control (standard configuration in spro). In me51n txn write a user exist to substitute new G\L for the given document types.

Hope this works.

regards,

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi john,

Budget check can be on Transaction group(PR, PO creation etc).

Budget can be configured at budget profile level which is assigned to project.

So as per my knowledge it is not Possible.

You may ask client why he wants this. We may provide some other way for same.