Dear Friends
I have one issue, system is not calculating dates as per routing time in lead time scheduling
my operation times are setup 1000hr ,m/c time-2000 hr & qty 1000 no
still the scheduled start & finish date is coming as same date ,pl guide me
I have checked settings of date adjustment in OPU3 & OPPQ