Hello all

I want to know about stock transport order

I can create order from Plant 'A' to Plant "B'

My requirement is

I want to create  order for two plants i.e

Plant 'A'- Requirement is 10 quantity

STO

should create for Plant 'B' and Plant 'C'.

Plant "B" -60%(6 Qty)

Plant "C" - 40% (4 Qty)

Note :In house material and Company code is same

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

sjeevan
Active Contributor
0 Kudos

Go to MM02 for plant A and enter the quota arrangement indicator in MRP 2 tab (select indicator which includes MRP).

Go to MEQ1 enter the material and plant A and then enter the valid to date. In the Item overview enter procurement type F, special procurement type U and Quota 60 and plant B as one line item and as second line item enter procurement type F, special procurement type U and quota 40 and Plant C.

former_member222080
Participant
0 Kudos

hello jeevabn

I have cretaed quoa and created the order

Thank you very much

sjeevan
Active Contributor
0 Kudos

Run MRP (MD02) and see if it's creating the STO's as per your requirements.

former_member222080
Participant
0 Kudos

Hello

I have executed the MRP fpr Plant A

I have maintained quota arrangment for Plant B as 60 and Plant C as 40

But palnned order created for the Plant B only. i.e) first liin the quota arangement

please provide some other solution

former_member222080
Participant
0 Kudos

Hello

I have maintained the maximum quantity and executed ,now order has created for both the plants.

Thank