Budgeting in SAP PS

154 Views

Hello Experts,

I have assigned Object Currency to the Budget Profile. So the User can budget in the Project Currency, rather than the Controlling Arear Currency. But SAP standard tolerance table only allows setting up tolerances in CO area currency, so the tolerances are setup in CO area Currency.

Question - Is there any way to assign the tolerances in the Object Currency?

Besides that we have the below problem.

When the activity is planned in CJ20N using the Object Currency, the amount entered in the material planning field is different to the amount displayed in the CJ30 screen under the planned value column.The controlling area currency displays the correct conversion amount in USD in all the columns in CJ30.

Eg: Amount assigned for Activity is 200CNY in CJ20N whereas the displayed value in CJ30 would be 150CNY. The number generated is quite random. Dont know why.

Has anyone else faced similar issue before?

Regards

T