Changing Profit center in MM01

1671 Views

While i try to change the Profit center system throws error

There are still open purchase order items or scheduling agreements

Message no. MM326

If i make this error message as warning, does it show any impact.........Becoz our material master now have wrong profit center assigned....My FI guy is ready to transfer the balances to the correct Profit center...