HI Gurus,

PR Release strategy modified to Header Level from Item Level.

Existing PR's not allowed to edit or force closing where Release strategy is not working.

Suggest best ways to correct old PR's.

Regards

Jaga

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Jagan,

Have you considered creating a new release strategy at header level instead of modifying the earlier one, instead lock the earlier release strategy (i.e at line item level) using cl20n /cl24n and change the status as "2".

Former Member
0 Kudos

Hi Jagan,

Have you considered creating a new release strategy at header level instead of modifying the earlier one, instead lock the earlier release strategy (i.e at line item level) using cl20n /cl24n and change the status as "2".

Former Member
0 Kudos

when you modified existing release procedure, there would be  inconsitancy in old PR or PO.

way to handle this, left that PR as it is so they that no release required them or do mass change of all old PR so that new release stratergy will trigger.