Hi,

I’ve scenario of I’m creating the process order and doing the batch determination in that order. In the order batches is assigned.

Ex: X batch assigned to XXXX material in PO1.

I created the another process order and I did the batch determination and assigned batches to that order.

Ex: X batch assigned to XXXX material in PO2.

X batch having the stock 100.

X-50 assigned to the XXXX for PO1

X-50 assigned to the XXXX for PO2.

I created the PO3 order. When I’m doing the batch determination system is proposing the X batch for XXXX material in PO3.

My issue is already X batch assigned to the PO1 & PO2. For PO3 it should not propose.

What I need to do for this.

Naren

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

If you want to batch determination as per orders do batch determination at the time goods issue.

This can be controlled using batch search strategy->strategy type-> ME01 (Movement type/Plant/Mat.No)

Regards,

srihari.M

Former Member
0 Kudos

Hi Sridhar,

You can use the batch determonation strategy using strategy->strategy type-> ME01 (Movement type/Plant/Mat.No....Try this...

Regards,

Sulabh