Viewing multiple simulation versions for project in single gant chart

Former Member
0 Kudos

Hello All,

Requirement is that my client wants to see Gant chart for Basic dates, Forecast dates and dates of the simulation version of the same project (so means 3 set of schedules) in a single gantt chart. Is this possible?

Regards,

Jatinder

Accepted Solutions (1)

Accepted Solutions (1)

0 Kudos

Dear Jatinder,

In the gantt chart, via button 'options' -> 'planning board' -> tab 'settings', you can select 'Set of Dates'. If you flag both basic and forecast, you will see both sets of dates. However simulation version data can not be accessed. Simulation version is based on different database tables not being read, when you call the planning board for an operative project.

Best Regards,

Edna

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello All,

I am able to get 2 Simulaton versions in single gant chart, by selecting VErsion Data in DB Profile,(T code - CN47). But now in the corresponding gantt chart, i see bars for both versions wth same color, is there any way to see the bars of different colors in different colors??

Regards

0 Kudos
Dear Jatinder,
Unfortunately there is no such possibility to see the bars in different colors.
The gantt chart you jump to from the information system transactions is not the planning board (e.g. when you jump from CJ20N) but a more simple version of a gantt chart.
Best Regards,
Edna