on 07-06-2012 5:34 AM
Dear All,
I have Prchase Material by preparing Capital Purchase Order (Internal Order) for one Project.
Received Material and used partly. Some qty. of MAterial is now not going to use it.
Project is still going on. I have not capitalised that internal Order.
Now i want to transfer some material from one plant to another plant.
Normally i use Tcode ABUMN to transfer material.
But as i have not capitalised internal order so i can not transfer to ABUMN.
So in this sceneriao (i.e non capialised material) how to transfer MAterial from one plant to another.
Regards
Swati Shah
Hi Swathi.
ABUMN this t code is use for asset transferred , company code to other company code.here material transfer not possible.
You can use T.Code MB1B and movement type 309 for stock transfer from one plant to another plan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
If you have used Internal order for capturing the capital items cost, then the AUC would have generated in the background. Would you check it once please?
At the same time, is the plant you are planning to transfer is in the same Company code or different?
Check the above
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Anybody can suggest some solution for above scenerio ?
Pl.....
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.