Skip to Content
0
Former Member
Jul 05, 2012 at 02:47 PM

SU25 in Quality & Production

378 Views

Hello All,

We upgraded our Development system from SAP ECC 6.0 to SAP ECC 6.0 EHP5.

For the Security upgrade, we executed the transaction SU25 (Steps 2a, 2b & 2c) in Dev system. In Step 2c, the system gave list of all roles in the Dev system for which profiles were to be generated, with the new authorization checks added in EHP5.

We had to generate profiles for all the roles in the system. The roles which contained the transactions for which the authorization checks were changed/ added, we adjusted them manually. For the roles, there were no authorization objects, we had to only generate the profiles.

Now we are going to upgrade our QA system. As per my understanding, we dont have to execute SU25 in QA system.

Only we have to transport the customer tables from Development (Step 3) & only the roles which were changed by addition/ change of new authorization checks.

Do we have to transport all the roles or only the new authorization check included roles?

or

Do we have to execute SU25 in QA system also?

Thanks in advance.

Thanks & regards,

Sagar