We have a project which apparently has budget as we can see it on CJ31 but when we do the Check we get the message

"No budget exists --> Availability control not activated".

We have no idea of why we are getting this message. Any idea?

Thanks

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

3 Answers

  • Posted on Jul 05, 2012 at 06:49 AM

    hi fortain,

    can you jsut put the screen shots of your budget profile and availability control settings and the error message you are getting.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jul 05, 2012 at 04:46 AM

    Hi Fortian,

    1. Try to activate Project availability control by CJBV(Run this in Background F9).

    2. Also Run CJEN for reconstruct project Info.

    Regards,

    Pranav

    Add a comment
    10|10000 characters needed characters exceeded

    • Hi Pranav Trivid,

      We find out this issue when trying to activated the availability control through CJBV, we always get the message:

      Availability control not activated

      Message no. BL001

      We have run CJEN but we are still getting the same message at CJBV and CJ31.

  • Posted on Jul 05, 2012 at 05:59 AM

    hi fortain,

    first check you budget profile (ops9). in there check activation type might be there you take 0 instead of 1 or 2.

    if it is ok. then go to t-code cjbw and deactivate availability control (cjbw) there and then run cjen it will reconstruct the databse tables for project info and then activate the availability control ( cjbv) and then again run the project construct info (cjen). it will work also refer this link

    http://help.sap.com/saphelp_srm40/helpdata/en/4f/b3e739e62b714be10000000a114084/content.htm

    can you please tell me which type of project your are working on.

    Add a comment
    10|10000 characters needed characters exceeded

    • Dear sulabh gupta,

      At the budget profile we have the option "1 Automatic activation during budget allocation" which has been working until now.

      I tried to follow the steps you told me, when running CJBW we get the message: "Availability control was not active for the following pro ..." and after all the steps we keep getting the same messages at CJBV and CJ31.

      Any other idea of what could be happening?

      Thanks to all

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.