on 07-04-2012 12:52 PM
Hello Experts,
I am facing problem in production confirmation goods movement in transaction co11.
In co11, only 101 mvt. type is getting proposed for some materials, when I am trying to save, message coming is (goods movement: 0 failed: 1).
I checked in MMBE unrestricted stock is available for this material.
How can I post it successfully or what can be the possible causes of error?
Please help.
Regards,
Shubh
Hi,
Please check
1. If batch is entered
2. storage location is maintained
3. No backflushing is used, if yes maintain batch and store.
Or else go to T. Code COGI and check putting your order number what is missing.
Regards,
Alok Tiwari
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi All,
Please correct me if i am wrong
If we don't maintain Auto GR for the last operation in routing the 101 movement type will not display in the Good movement at time of conformation (co11/co11n/co15). so the production-order status will cnf/pncf. Again we have do the GR manually by using T.Code MB31 or MIGO. why you all giving suggestions this might be the reason.
what effect will be if Backflush indicator is not active for the components for 101 movement type getting error (goods movement: 0 failed: 1)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Vempati Sundeep,
If backflush is not active for the components means(either in the order or else in the material master
or else in the routing),then you have to perform GI(261 movement) manually using MB1A or else
MIGO against the reservation no of the order.
GI will be independent of order confirmation,which means you can issue the components before or
after the confirmation,but the standard procedure would be issuing the components,then confirmation
followed by GR for 101 movement.
Regards
Mangalraj.S
Shubham Agarwal wrote:
In co11, only 101 mvt. type is getting proposed for some materials, when I am trying to save, message coming is (goods movement: 0 failed: 1).
There could be a few reasons,
1) first check if you have components assigned to that operation. (CO03 >> Component Overview)
2) Second check, if backflush indicator is active in the production order (CO03 >> Component Overview)
Now, coming to the error (goods movement: 0 failed: 1) the most probable cause of this error would be not maintaining the goods receipt storage location ( Co02 >> Goods Receipt (tab) >> Stor. Loc.) There may be other causes also which you need to check in COGI by entering the order number.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Shubam,
Issue –
During CO11, only 101 mvt. type is getting proposed for some materials, when saving, message coming is (goods movement: 0 failed: 1).
Solution –
1) You can check in COGI for all the materials of Goods issue why good movement had failed this for 261 material. Normally goods movement fail due to deficit of stock, material stock not present the proposed storage location etc. You can correct these errors.
2) You are saying that 101 mvt. Type is getting proposed for some materials. It cannot happen. It will be only for One material i.e. the header material for which you have made the production material. Check that you have selected auto GR, in last operation.
3) Backflush materials GI will be done by CO11. System will take care for backflush material for 261 movement.
4) For non backflush materials, you need to issue through MIGO or MB1A against the production order 261 movement
Also refer to suggestions by Mangalraj, Senthil and Sundeep.
Hope its clear.
Regards,
Srini
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Shubham,
Do you intend to post the Goods Issues (of the BOM components) also during the confirmation entry?
Please check the transaction COGI - to find the list of failed goods movements, reasons,... and you can handle(post) them from the same transaction, once the issue(reason) is addressed.
Regards,
Senthil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Agarwal,
As mangalraj in the third point
The errors might be like below
1. Enter the Batch
2. Posting only possible in periods 2012/06 and 2012/05 in company code 1000
3. Enter Storage Location
And 101 movement type is for good-receipt, so it don't matter if stock is available or not.
Thanks
V.Sundeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Shubham,
1.If automatic GR is set through the control key of the operation(last operation) or else through the
production scheduling profile the system proposes 101 movement - GR for the production order -
material in CO11/CO11N.
2.If backflush is set at the material master level o else in thr routing-component assignment or else in
the order then the system proposes 261 movement in CO11/CO11N.
3.All the failed goods movements can be checked in T.Code COGI along with the reason for of the error.
4.Check the error,rectify and post the goods movements in COGI.
Regards
Mangalraj.S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
10 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.