Change Shopping Cart and update Purchase Order

Hi experts

i'd like to know if there is a way in order to change a Shopping Cart "father" of an existing Purchase Order and update the same PO.

The issue is that if i change on ECC 6.0 the PO, adding for example a new line, the goods receivement gets an error.

So i thought to change, first of all, the Shopping Cart and then update the existing PO in order to have a correct goods receivement. Is there a way to do that?

with kind regards

andrea

Add a comment
10|10000 characters needed characters exceeded

Related questions

5 Answers

  • Best Answer
    Posted on Jul 04, 2012 at 11:19 AM

    Hello,

    When a shopping cart has been approved it cannot be changed anymore. I think you need to create a new shopping cart and (i assume you are on the classic scenario) add the newly created purchase requisition to the existing PO. After that you should be able to receive the goods in SRM.

    Kind regards,

    Antoinette

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jul 05, 2012 at 07:00 AM

    Hi Andrea,

    The shopping cart cannot be changed once approved. If you are using extended classic scenario, then you can change your PO in SRM and the changes will flow into ECC.

    Regards,

    Nikhil

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jul 05, 2012 at 07:17 AM

    Hi Andrea,

    SRM support 4 technical scenarios

    1. Classic Scenario
    2. Extended Classic Scenario
    3. Standalone
    4. Decoupled.

    If your scenario is Classic then once PO is created for that SC then we can't do any changes to the SC.

    In Extended Classic you have the provision to do that. Once you change the SC then it goes for an change version of the approval and once approved those changes get reflected in ECC.

    

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jul 05, 2012 at 11:50 AM

    Am not sure ,why you are following the SC change path? GR's are based on PO , not SC . Would like ask below questions:

    - for PO change , is there any release strategy designed in ECC? if yes, then after approval of changed version of PO , you are entering the GR?

    - could you publish the error you are facing in GR

    Also , suggest you to test the reported scenario for direct orders as well in ECC and check if there by mistake Delivry. Compltion flag is getting set at PO level for SRM orders.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jul 05, 2012 at 08:13 AM

    Hi at all

    thanks for your cooperation

    but... in classic scenario also implementing BBP_DOC_CHANGE_BADI in SRM and BAPI_PO_CHANGE ( BAPI Function Module ) in R/3 is impossible to change?

    with kind regards

    andrea

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.