on 07-03-2012 3:12 PM
Hello,
Due to the project situation and inherent limitations with PDS, we are using PPM instead of PDS. There is a concern that SAP may not support PPM in future. Does anyone have a clear answer to the concern on SAP's support for PPM?
Regards
Manotosh
Hi Manotosh,
SAP support say that PPM will not supported on future releases, but at moment, PPM still running. In my opinion will work forever.
But why you are working with PPM? Because PDS has more features than PPM (like "Min. Send-Ahead Quant." ).
I test PDS and PPM, but use only PDS.
Best regards,
Mengue
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.