Material Staging in Discrete Mfg.

Former Member
0 Kudos

Hi All,

For production orders, getting below error while staging(creating replenishment) missing parts using MF60;

Msg.typ Application area     MsgNo Message text                                                             

                                                                                                                   

I         RMPU                 305    Rep. Elmt  WM Pick: reservation number 0000674337, item 0001                

E       RMPU                  311   WM material staging for production order reservation not possible        

I         LP                       129    Material number:   Plant:   Batch:                                       

E        LP                      152    Error during determination of control of WM/PP staging

If MF60 is not correct interface in discrete manufacturing, is there a way to run create replenishment in mass?

Thanks.

Pradeep

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Pradeep,

You can use pull list for Production Orders also. Pull list MF60.

Few basic understanding on pull list

  • What is the function of Pull list ?

      Pull list is used to withdraw the components from Main storage location to   the issue storage location. Issue storage location is Prod. storage location.

      Pull list used to control the flow of components required for in-house manufacturing.

      It is assumed that the components required are already (procured or produced ) made available in the Main storage location and to be transferred now to production storage location.

      Pull list takes into account the dependent requirements generated from the planned orders of the parent parts and stocks of the child component is checked at the production storage location.

      Pull list calculates the quantities of the missing parts.

    

  • What are the missing parts?

      Missing parts are the parts which are required at the production storage location as per the dependent requirements generated and these parts are not available at Production storage location.

  • What is issue storage location and Replenishment storage location ?

     The issue storage location is the place from where the components are going to back flush , at the time of confirmation ( GR ) of parent.

      Replenishment storage location for Externally procured part is the ‘storage location for EP ---- on MRP 2 view.

      The main storage location  ( where components are stocked )is also called as replenishment storage location. System calculates the replenishment elements for the missing parts.

       The Process of executing the Pull list and getting the material is known as Material staging. 

      The issue storage location should come from the master data to the dependent requirement which has come from the planned order.

      Issue storage location needs to be maintained in BOM or Material master.

Regards,

Srini

Former Member
0 Kudos

I have all the settings maintained at master data level and config. Using "Staging type: WM pick Parts", I got missing components list but when I started creating replenishment and execute staging got error as mention in my original message.

Staging type: WM Pick Parts is the correct staging type for production orders? is there any config./settings specific to wm pick parts staging type?