FM and GM Availability Control for CO Cost Allocation

Hi All,

I run cost allocation with Funds and Grants Management activated in my system, however, the allocation figures get posted without any effect on the budgets in FM and GM. I was wondering if there is any way to activate budget availability check for cost allocation process in Funds and Grants Management. I will also like to know how to go about this setting or any other way to achieve budget checks for cost allocation process.

Thanks for your help.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Jul 02, 2012 at 09:45 AM

    Hi,

    You have to switch the integration between FM and CO via IMG - Public Sector Management - Funds Management Government - Actual and Commitment Update/Integration - Integration - Integration with Cost and Project Controlling

    Regards,


    Eli

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Minghong,

      Please clarify - does AVC check all CO-postings in your system? What about Internal Order settlement or cost allocations? Have you implemented any ABAP-enhancements to do that?

      Regards,

      Oleg Tolstashov

  • avatar image
    Former Member
    Mar 20, 2013 at 02:47 PM

    Hi, Chukwukadibia!

     

    Kindly let me know - have you solved your issue with FM AVC for CO-postings?

    I'm facing the same problem now. Would like to have a suitable solution.

     

    Regards,

    Oleg Tolstashov