FM Availability control objetcs

here client is using superior commitment and commitment concept

Fundcenter

superior commitment item

Commitment item

Budget will given for both Superior commitment and commitment item level

Eg:SCI=A

CI=1

CI=2

Ci=3

In fmbbc budget Given to SCI(A)=100000

For CI(1)=10000

intially system is allowing to post more than Rs.10000 for CI(1)

so i have crated in Derivation Rule for control object i gave rule to exclude from Superior Commitment item (which is a separte control Object)

now system is stopping him use budget from Superior commitment item.

but the problem is suddenly in fmavcr01 the superior Commitment item(A) budget missed and even giving budget now also document is posting but not updated at SCI(A) level in fmavcr01.and it is showing now alram mode

i am unable to trace the problem.any config problem or anyother. i had run FMAVCREINIT ALSO BUT NO USE.

please provide the solution

it is very much appraciated.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Jun 29, 2012 at 09:37 AM

    Hi,

    To make it more clear, please send screenshots from your AVC strategy for control objects, FMAVCR01 report, document in question with FM assignment.

    Regards,


    Eli

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.