SAP SD Changes: if ECC 4.0 upgraded to 6.0

Hi experts,

Will there be changes in theconfiguration of SAP SD if 4.0 will be upgraded to 6.0?

Will it be fresh back to start like implementation? And what will be frequent ask questions for this upgrade for SAP SD module.

Thank you.

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Posted on Jun 29, 2012 at 06:10 AM
    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      So basically sir, the set up of the customer for SAP SD will remain and carried over.

      And enhancements on configurations will be simply based on the additional features provided by the ECC 6.0 such as if the customer are willing to activate new features such as the Credit Management module of SAP. Kindly confirm.

  • author's profile photo Former Member
    Former Member
    Posted on Jul 01, 2012 at 02:50 PM

    Hi ,

    difference between 4.7 and ECC 6.0

    1. changes in assignments in Enterprise structure.

    2. Consistency check is more detailed now, compared to 4.7, and Look and feel also changed.

    3. Document flow -Look and feel changed

    4. In the order at item level the tab in ecc 6.0 is order data, whereas in 4.7 it was Purchase order data.

    5. In sales order Item conditions, the status indicator (Green signal) are introduced for all condition types with ecc 6.0, but in 4.7 it was only for the output conditions.

    6. VL09 - Goods issue reversal has added new icons in ECC 6.0 such as "Details, sort in ascending/descending order, set filter,word processing, local file,Mail receipt,change/sheet/save layout".

    7. Quotation, Order, Contract, Billing lists,

    Transaction code changed.

    Va25 to VA25N

    Va05 to VA05N

    VA45 to VA45N

    VF05 to VF05N

    The look and feel also changed with new selection criterias.

    8. In VF04 Selection criteria has been compressed in tabs, and new default data tab is included.

    9. In 4.7 it was not possible to control division specific credit management but in case of ECC 6.0, credit management can control division specific.

    10.SAP moved a lot of reports to the ALV format in ECC6.

    Regards,

    Patchala

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jul 02, 2012 at 08:52 AM

    It seems you have not searched in Google to get more informations since in the past, many times, this has been discussed. Moreover, you have not indicated whether it is ONLY a technical upgradation or also includes functional upgradation. If it is going to be only a technical upgradation, then there is not much difference in the features from SD perspective. Only you will find some difference in transaction screens.

    G. Lakshmipathi

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.