During infopackage loading for data source 0CO_PC_PCP_30 we are getting error :

"Material ledger currencies were changed"

Long Text :

Material ledger currencies were changed

Message no. C+039

Diagnosis

The currencies currently set for the material ledger and the currency types set for valuation area 4907 differ from those set at conversion of the data (production startup).

System Response

The system does not allow you to post transactions after changing the currency settings to ensure consistency.

Procedure

Replace the current settings with the those entered at production
start-up.

If you wish to change the currency settings, you must use programs to convert data from the old to the new currencies.

Inform your system administrator.

Can anyone please suggest what can be issue and how this can solved.

Thanks,

Deepak