Former Member

Order reschedule on DS board

Hello Gurus,


Trying to reschedule planned orders on DS board for FG product & order was scheduled as per requirement however found that
system doesn't reschedule orders for dependent semifinished materials till last level of BOM

Is the std behaviour of the system if yes than How to align orders till last level of BOM with FG order.



Appreciate your inputs!

Thanks in advance

Regards
Milind

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Jun 25, 2012 at 11:57 AM

    Milind,

    Yes, this is standard in most APO scenarios. Actually, it is standard in most planning systems, not just SAP APO.

    In some companies, after rescheduling the FGs orders, they will run a mass heuristic to realign the SFG and Raw Material Supply elements to the shifted FGs dependent demand, Other companies who need instantaneous feedback will use a planning procedure that automatically runs a heuristic when such changes are made.

    Best Regards,

    DB49

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jun 26, 2012 at 08:55 AM

    Hi Milind,

    You can run SAP_PP_010 top down heuristics from DS board to adjust dates post reschduling.

    Also you can try rescheduling with strategy parameters checkbox consider dynamic pegging checked

    Regards,

    Santosh

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi DB49/Santosh,

      Could you please share set up for planning procedure to run heuristics automatically

      I tried also SAP_PP_010 in planning run with object as a order & selected all the orders However systems has done rescheduling just one level below instead of all the levels.

      Could you please share set up for post rescheduling with heuristics.

      Appreciate your inputs!

      Regards

      Milind

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.