Hi,
I am using REM production scenario for 2 materials without VC. Each material has same 5 characteristics and the specifications are different from each other. I have done to following:
1) Created the required Characteristics using (CT04)
2) Created one Batch Class(023) using (CL01)
3) Assigned the created characteristic to the Batch Class (CL01)
4) Assigned the batch class to material master in classification view. (MM01)
5) Created MIC with reference to above created Class characteristic (QS21)
6) Created inspection plan with MIC (QP01)
I am able to update the inspection results to batch master record.
My requirement is how to maintain the specifications in inspection plan for the 5 characteristics for both the materials without using VC.
Anybody can please help me.
Thanks & Regards,
Devaraj