on 06-20-2012 7:46 AM
hi:
I have a requirement about alternative parts...
Alternative parts A&B:Due to product update and cost reason,client want to plan fcst on B and PO continue to consum stock f A. Since both A&B would be in the same BOM ,I cann't find a suitable aternative method for it..Someone told me it is possible to make it in SAP..We can plan on B and PO consume A...Anyone can give me some tips...thanks..
This is use-up effectivity -Engineering change.
In the material master of A, define B as "Follow up material"
Addtionally pupulate
Discontinous Ind=1
Effective out-date= Earliest date ECN can be effected.
MRP will ful fill all requirement of A with material A till Earliest date or Stock of A is depleted. After projected stock of A is reaches 0, purchase req of B will be generated in advance.
Depending on actual consumption/issue...Effective date of change will be same or later that Effective out date.
You write abap to take report when actual chnage occured /from which date & change BOM using ECN retrospectively.
Note that , if demand increases & projected stock of A reaches 0, system will raise PR before 'Effective out Date'. So be careful in defining Effective out date. You don't need to calculate effective out date... it is earliest ECN can be implemented. Rediness of vendor, Engineers, Shop floors rediness,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi Yang,
Forecast is always under FERT... so if A & B are raw materials or HALB....There is only dependet requurement for A & B. I don't understand why you are using word forecast from A & B.
With above solution all dep req will be under A(Since BOM is not updated yet), but MRP is intelligent enough to pass excess requiremet to B & generate purchase req. for B. if your meaning of forecast of B is future purchase req...you will make it .
Please award point for this
Jatin
Hi Yang,
Dependent requireemnt is MRP element....Technical object for MRP to work across BOM level... It doesn't represent or map to any business entity... your client should only evaluate end result.. i. e. Purchase Requsiitions are going out on correct part number.
if your client is not so expert & doesn't go thro' detailed evaluation of MRP/Stock requiremnt list, it would not matter at all since Purchase Req. outputs are all correct.Many of customer only output PR list... & don't care as long as ordering is perfact.
Please award points for this.
Regards,
Jatin
Hi,
Please try alternate BOM item in BOM.
An item used as an alternative to one or more BOM items. Alternative items in a BOM that belong together are assigned to an alternative item group.
Please check below link:
http://help.sap.com/saphelp_46c/helpdata/en/ea/e9b3eb4c7211d189520000e829fbbd/content.htm
http://scn.sap.com/thread/781270
Regards,
Alok Tiwari
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
use alternative item grouping function from BOM.
http://help.sap.com/erp2005_ehp_06/helpdata/EN/ea/e9b3c44c7211d189520000e829fbbd/frameset.htm
please search forum you will many threads in detail for same.
Thanks
Ritesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.