Dear Friends,
As per your guidelines from SAP, we have executed CJEN Transaction code to
rebuild the project info data base for our case in Production system
for the specified project. But after execution we found that the entire
Distributed budget at Header Level, Distributable Budget at WBS Element
level & released budget values are missing in all Budget reports like CJ31.
The Distributable Values are also missing in report you have mentioned
BPFCTRA0 (Analysis Program for Active Availability control) in your
Previous replies. Whereas Assigned values are showing in all Budget
Reports.
Please help us how we can get back all the Distributed budget, Distributable Budget & released budget values which are missing in all Budget reports. Before all the values were there and all the budget reports were correct with Distributed budget at Header Level, Distributable Budget at WBS Element
level & released budget in specific project.
Kindly request the exact process how i can solve my problem mentioned above.
Thanks & Regards,
Naveen Kumar.