Dear Friends,

As per your guidelines from SAP, we have executed CJEN Transaction code to

rebuild the project info data base for our case in Production system

for the specified project. But after execution we found that the entire

Distributed budget at Header Level, Distributable Budget at WBS Element

level & released budget values are missing in all Budget reports like CJ31.

The Distributable Values are also missing in report you have mentioned

BPFCTRA0 (Analysis Program for Active Availability control) in your

Previous replies. Whereas Assigned values are showing in all Budget

Reports.

Please help us how we can get back all the Distributed budget, Distributable Budget & released budget values which are missing in all Budget reports. Before all the values were there and all the budget reports were correct with Distributed budget at Header Level, Distributable Budget at WBS Element

level & released budget in specific project.

Kindly request the exact process how i can solve my problem mentioned above.

Thanks & Regards,

Naveen Kumar.