Hi Expert,

System Info - SRM 7.0 and ECC 6.0 701 Release

http://help.sap.com/SCENARIOS_BUS2008/helpdata/EN/61/1775eecdd343c9b4c28db68d1d4bd8/content.htm

As per the above link I have configure every thing, enhance the BADI and added BOR's every thing. But when I am checking the the PR after creating in MM and releasing it is not available.

1) Any further setting need to done more?

2) I am checking in Table BBP_PDBEI in SRM system for be_object_id field ?

3) Need to trigger any thing to transfer the PR from MM to SRM?

Please guide me. Waiting for ur valuable help

Thanks and Regards,

Farooq

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Jun 16, 2012 at 12:37 PM

    Please check in SWEL transaction whether the workflow WE53800009 is triggered successfully. Please note after PR approval only the event triggers to trigger the workflow.

    If yes then check in XSMB_MONI (ECC system) if the XML is generated and successfully passed to PI.

    If yes then check in SXMB_MONI (SRM system) if the XML is generated successfully.

    With Regards,

    Malay

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.