Budget Error generate by System

Former Member
0 Kudos

Check the Same

System have Total budget Rs.

12359842.90

Actual :

10581022.42

Commitment :

18090

So Available Budget Rs.

1760730.48

  But when we Create PR/PO of Rs . 58,000/- Rs. System Generate Budget Exceeded Error. Plz. Provide Solution.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Kindly check the released amount for your current period(S_alr_87013560).

If it still occurring then check for financial year specified in Performance assistant box.

former_member195427
Active Contributor
0 Kudos

Hi Mayoor,

               Please run T-Codes CJEN & CJBN respectively and then try your logistics postings.

If it does not resolve your issue , run program RKANBU01 & RKACOR04.

Hope it helps you..

Regards

Saurabh

former_member221039
Active Participant
0 Kudos

Check some pr lines deleted with commitment. deleted pr lines commitment can not be seen.