Former Member
Jun 13, 2012 at 07:45 AM

Assignment of new maintenance pack to strategy

10 Views

Hi Experts,

I have to assign a maintenance Pack to a strategy. see the below example:

Pack no. Cycle length unit maintenance cycle text Cycle short text Hierarchy Hierarchy short text

1 40 H 40 HOURS 01 1 1

2 100 H 100 HOURS 02 2 2

3 150 H 150 HOURS 03 3 3

4 200 H 200 HOURS 04 4 4

5 250 H 250 HOURS 05 5 5

6 300 H 300 HOURS 06 6 6

I need to assign a package of 125 hours. I am not sure how can i do this. Should i enter at the end with cycle short text and hierarchy as 3, in that case do i need to change cycle short text and hierarchy of all other downwards as there is already one with same cycle short text and hierarchy. What will be the impact on orders. Can it be done directly on production server as i think its not requried to be transported from development.

Regards