Maintainence of calls for Stability Study.

Hi Gurus,

We are facing following problem in maintaining calls in stability study.

The material which is considered for the Stability study is kept under different storage conditions for different periods of time, which may be in days, months, years.

When, the material is kept in a particular storage condition as per the predefined time period, the system calls for inspection and gives the date for next inspection based on the predefined interval.

The main problem occurs when the next inspection date for a stability study falls in an leap year. Whenever, the year is a leap year the system should identify and correct the next inspection date.

For e.g. If a material under stability study has inspection interval of 1 year and the study is to be carried out over a period of 6 years. Suppose the initial start date of the stability study is 1st April 2010, and the next inspection date as per the predefined time period is 1 year (365 days), therefore the next inspection date would be 1st April 2011.

Since 2012 is a leap year, the system should have calculated 365 days and given the next inspection date as 31st April 2012. However, the system gives the next inspection date as 1st April 2012.

Please let us know your valuable suggestiosn with regard to the problem.

Thanks in advance for all your help!

Prashant S

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jun 12, 2012 at 05:29 AM

    There is certainly one way , under maintenence plan header in IP01 ,there is provision of entering factory calendor.

    You can define your own calendor as per your requirement.also you can have your own rule for the calendor.you can take care of your requirements here.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jun 12, 2012 at 05:47 AM

    Select 'Time - key date' for scheduling indicator in maintenance plan.

    For scheduling, one month is always 30 days long in the standard system.

    Refer F1 help

    • Time

    Today's date: 04/10/1998

    Next planned date: 03/11/1998 -> Today's date + 30 days

    • Key date

    Today's date: 04/10/1998

    Next planned date: 04/11/1998 -> Always on the 4th of the month

    • Factory calendar

    Today's date: 04/10/1998

    Next planned date: 16/11/1998 -> Today's date (or next work day) + 30 work days

    Regards, DoWook KIM.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.