why PO is not required in Pipeline Procurement? Please explain in Detail?

Hi Experts/Guru's

why PO is not required in Pipeline Procurement? Please explain in Detail.

with an example also.

Thank you

venu

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • Best Answer
    Posted on Jun 11, 2012 at 04:21 PM

    Pipeline Material flows directly into the production process from a pipeline for example - oil, tap water or from another similar source say electricity

    A material from the pipeline is always available; i.e. it can be withdrawn from the pipeline at any time and in any quantity such is the agreement made between you & your vendor,

    So since Material is always available at any point of time so PO is not required in Pipeline Procurement,

    Process flow for Pipeline Purchasing will be,

    1. Create a Pipeline material - MM01

    2. Create Pipleline Inforecord - ME11

    3. Maintain source list if required - ME01

    4. Posting Goods issue from pipeline - MIGO (Movement types : 201 P, 261 P, 281 P, 291 P)

    5. Settling Pipeline liabilities - MRKO


    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jun 11, 2012 at 04:23 PM
    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jun 11, 2012 at 08:13 PM

    do you do that in private with your energy and water suppliers?

    what quantity would you enter? how often would you create such order?

    it is a untility supply contract, not for a fixed quantity often not for a fixed price or even period. it automatically prolongs if you do not resign. Because of this you cannot use a quantity contract in SAP. the info record is just enough.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jun 12, 2012 at 01:44 AM

    Hi,

    For pipeline procurement, you should have a contract or PO( a commited document with vendor-logically) and all other price details flow from inforecord(for pipeline).

    Refer links:

    http://help.sap.com/bp_chem603/BBLibrary/HTML/903_EN_DE.htm

    http://scn.sap.com/thread/1055430

    Regards,

    Biju K

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.