Error in Project Settlement

Dear Sir,

I have created a customer project for which I had maintained Settlement profile and settlement rule(g/l settlememt) .

When I execute Cj88 with processing type By Period ,the system gives the error as " Either the sender is already settled or there is nothing to settle".

I anyone guide me how to reslove this issue?

Regards

Prashant

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Jun 11, 2012 at 05:45 AM

    The error is self explanatory. The reason could be that since you are trying to settle By Period system is not finding anything in the particular period that can be settled. I would suggest you to run CJI3 for the object that you are trying to settle. Run this for the period you were mentioning in CJ88 and see if there are any costs available that can be settled.

    Check this and revert.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Prashant,

      Please check while you are doing settlement( in CJ88) is Order Check box is marked or not if not Please mark...and try to give only one WBS element not for Project Defination...

      Try and Revert....

      By

      Suma😊

  • avatar image
    Former Member
    Jun 11, 2012 at 09:46 AM

    Dear Prashant,

    Cost settle only after issue of material.

    So try to issue that material for WBS and then run settlement.

    Hope you have selected with hierarchy & orders.

    Settlement period must match with issuing date.

    Regards,

    Pranav