Enablement of direct material PO creation from RFx in classic scenario?

Dear Experts,

We are in classic scenario in the environment of SRM 7.01/ECC 6 EHP5. We have a requirement of triggering direct material PO from a RFx document during the awarding of a quote. On approval of the quote, the quote may be converted to a purchaser order in the backend system. It is currently taking the account assignment based on the SRM ORG Assignment and GL account defined in the settings. So, the system is taking it as an indirect material PO.

How to enable the direct material PO from a RFx triggered in SRM?

Secondly, How to control the plant assignment to the Purchase Order? An Org unit may be responsible for multiple plants (defined in the extended attributes), however, the material is treated as a direct material only one plant? How to control the plant assignment during the PO creation since an RFx document does not pass the plant?

Thanks and regards,

Ranjan

Ranjan Sutradhar

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jun 13, 2012 at 06:52 PM

    Hi Ranjan,

    If you initiate the RFx from the Shopping cart it will take the account assignment associated to a SC. Wouldnt that work for you?

    In the shopping cart if you can make it to indirect (free text procurement) and set the sourcing indicator such that it comes to the sourcing cockpit and then create a Rfx and get quotes on it and then create a PO out of the Response and I believe you will see the account assignment as that of the shopping cart.

    We have done something similar to this where in we have converted the PO that gets created into a framework PO( limit type) through code.

    Regards,

    Naveen

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jun 14, 2012 at 08:30 AM

    Further to the scn forum http://scn.sap.com/thread/3184410 one workaround can be to create a z program in ECC to change the PO account assignment category "U" or "K" (PO created from SRM) to blank selectively (provided material is a direct material in the plant).

    System takes the first plant available for the user organization structure.

    There can be provision in the above program to change the plant. But there will be some manual intervention.

    With Regards,

    Malay

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.