For an international cylinders filling center, I'm facing this organization.

From an production point of view Finished Good1 and component1 are the same whereever they are stored.

As the cylinders come from different countries, they have to return, once filled, to their respective country.

Finished Good1 = full cylinder, component1= empty cylinder, component2= raw material

So, as on the floor shop, they are stored in different area, per country, I've decided to manage these products into several storage locations instead of increasing the number of material codes.

I created 2 MRP areas for storage locations to plan independently the requirements , 2 alternative BOMs to consume component1 from the storage location 3 or 5.

Now, I don’t know how MRP selects the alternative BOM according to MRP areas. Alt1 for MRP area1; Alt2 for MRP area2

Do you have any ingenious idea?

Regards.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Jun 07, 2012 at 06:39 PM

    Hello

    You may create a production version for each MRP area and create an implementation of BAdI MD_MODIFY_PRODVERS using your own logic to select the production version.

    BR

    Caetano

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.