Hi experts,

There are both systems available like SAP R/3 and SCM APO. Master data is created only in SAP R/3. When i have to plan particular FG material 1, i wll maintain parameters like MRP type = X0 for particular FG material 1, raw material 1 so that planning will be done only in SCM APO so planned orders will be created in SCM APO through sales order and confirmation will be done in SAP R/3.

Case I - When I change master data for FG material 1 like MRP type = Pd, strategy = 10 and relative parameters of Make to stock scenario, PIR created and try to planning execution through MD02. But in MD02 only FG material 1 is showing and not component raw material 1so planned order for FG material 1 is created but Purchase requistion for raw material 1 is not created. Only dependant requirement is showing in MD04 for raw material 1.

Case II - Now i am created total new material masters like FG material 2 and raw material 2, maintained all standard parameters in material masters for Make to stock scenario. Again PIR created and MRP run through MD02, but same problem like purchase requision not created,

So what is the basic reason for not planning in R/3 but done in SCM APO?

Suggest me.

Regards,

Nitin Nerkar

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Posted on Jun 06, 2012 at 01:33 PM

    Dear,

    Couple of checks,

    1. Is there any Stock for material ?
    2. Have you maintained Purchasing data for these raw material?
    3. Do you have MRP view with correct MRP type is define in system.?
    4. Planning file entry is created for these material cross check in MD21.

    Please check and come back.

    Regards,

    R.Brahmankar

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jun 06, 2012 at 04:04 PM

    Nitin,

    Case I - When I change master data for FG material 1 like MRP type = Pd, strategy = 10 and relative parameters of Make to stock scenario, PIR created and try to planning execution through MD02. But in MD02 only FG material 1 is showing and not component raw material 1so planned order for FG material 1 is created but Purchase requisition for raw material 1 is not created. Only dependent requirement is showing in MD04 for raw material 1.

    This is normal. You have decided to plan the FG in ERP, but you have left the planning of the RM in APO. If you wish for the RM to also be planned, you will have to execute a planning heuristic in APO.

    By the way, this scenario is uncommon. Most companies who decide to split planning between ERP and SCM elect to plan the higher levels of the BOMs (more critical) in APO, and leave the lower level materials (less critical) to be planned in ERP using a consumption MRP type.

    Case II - Now i am created total new material masters like FG material 2 and raw material 2, maintained all standard parameters in material masters for Make to stock scenario. Again PIR created and MRP run through MD02, but same problem like purchase requisition not created,

    What are the MRP types of FG2 and RM2? If either of these are X0, have you generated and activated Integration Models?

    Best Regards,

    DB49

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.