We create Order and assign Task lists by selecting Extras -> Task list selection -> Direct entry : selecting General Task list , Group and Group counter is given: Task list is included for one user, but for other user a pop up comes - OPERATION SELECTION USING WORK CENTER/REPLACE WORK CENTER.

We checked both the user's settings : Extras -> Settings -> Default Values -> Control : No selection in Task list transfer for both the users. But how come this screen pops for one user and not for other user. Is there any User Role authorisation is involved.

Kindly suggest.

Raja

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

This is a user specific setting. While in any Service Order, Goto Extras--> Settings --> Default Values.

Go to the Control tab. Manage your Pop-Up for Task List in 'Task List Transfer". These are the options that dictate if the user should or should not get a Pop-up while including a Task List.

Hope this helps, let me know.

Jack.

Former Member
0 Kudos

Hi Jack,

As I mentioned earlier, for both the users, checked both the user's settings : Extras -> Settings -> Default Values -> Control : No selection in Task list transfer for both the users.

But how come this screen pops for one user and not for other user.

This is the issue. Is there, any other settings related to User or Authorisation related.

Kindly suggest.

Raja

peter_atkin
Active Contributor
0 Kudos

If the settings are the same, then it could be a GUI issue..

Try getting the users to log onto each others PC and check again.

PeteA

Former Member
0 Kudos

Hi PeteA,

It may be related to Table updation TPMUS.

Kindly suggest

Raja

Former Member
0 Kudos

We had a analysis, related to the issue.

User 1: who gets the pop up - As not yet defined any selection in Extras--> Settings --> Default Values -> Control from starting of the usage.  Till then the user is not got updated in the TPMUS Table.

So that the User gets the POP UP.

User 2: who is not getting the pop up - Defined the selection earlier in Extras--> Settings --> Default Values -> Control, then this selection was deselected.

As this User name gets populated in the Table TPMUS and no selection the POP UP is not getting populated. Until we define the selection, only we get this POP UP.

Thanks for your feed back.

Regards,

Raja

Answers (4)

Answers (4)

Former Member
0 Kudos

Hi

You have to follow

Extras--> Settings --> Default Values. 

Go to the Control tab. Manage your Pop-Up for Task List in 'Task List Transfer

Make sure both the users have simmilar version of GUI

Former Member
0 Kudos

Are both using same data like plant, work center, task list, etc.,?

Former Member
0 Kudos

Hi,

All the data are same for both the Users.

Order type, Plant, General Task list, Counter.

Can you please suggest.

Thanks

Raja

Former Member
0 Kudos

I hope work center also would be the same. Please provide us some screen shots for those users, so that we can get some better idea.

shailendradupadhyay
Contributor
0 Kudos

Hi

What is the order type, both the order having same order type or different or both user using a single order.

Shail

Former Member
0 Kudos

Hi,

All the data are same for both the Users.

Order type, Plant, General Task list, Counter.

Can you please suggest.

Thanks

Raja

Former Member
0 Kudos

Hi,

Can you pls let us know the message no.??

rgds