Skip to Content
author's profile photo Former Member
Former Member

Initiating an Intra Company STO from Sales Order

Dear SMEs,

Here is my requirement.

We have two plants 1234 and 2345 under one Company Code.

1. 1234 has a small Warehouse, so whenever a Sales Order is created from 1234,during delivery it should check for the stock in its warehouse. If sufficient stock is not available in 1234 relevant warehouse, then a Intra Company STO has to be initiated for stock transfer from 2345 plant to 1234(for the difference quantity) provided if sufficient stock is available in 2345 plant relevant Warehouse.

2. Both the plants 1234 and 2345 are Warehouse managed.

3. Can we achieve this functionality with out any custom abap development in the exit ?

4. Now the goods should be shipped from 2345 plant to 1234 plant and not to the customer location.

5. Goods will be shipped to the customer from 1234 plant like any other normal delivery.

6. Customer also has an option to update the order before Order cut off time.

Thanks,

Ram.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Jun 04, 2012 at 03:08 AM

    Hi,

    You have two plants 1234 and 2345 under one Company Code in which Receiving Plant 1234 and Supplying Plant 2345.So plant 1234 is act as customer and plant 2345 is act as vendor but actually material will be shipped to the actual customer from 1234 plant like any other normal delivery after STO process complete from plant 2345 to plant 1234.

    1.Create STO in ME21N with at Receiving Plant 1234.

    2.Create Delivery in VL10B from Supplying Plant 2345

    3.Go for PGI in VL02N from Supplying Plant 2345.

    4.Do GR at Receiving Plant 1234 based on Outbound Delivery at Receiving Plant

    After above steps , you can shipped the material to the actual customer from 1234 plant by creating sales order,delivery,PGI and billing to customer

    Regards,

    Biju K

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.