Hi,

When I am running MRP using MD02 for individual material, purchase requisitions are getting created, but for the same plant when MRP is run using MD01/MDBT with the same parameters as in the case of MD02, purchase requisitions are not geting created. In MD04, only PIRs are showing. Please throw some light as to why it may be happening.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi

Usually the cause is that the corresponding planning file entries are not set for the material (transaction MD21). You can find further information on planning file entries in notes 205681, 371016 and 553746. In order to check which materials the total planning run plans, it is recommended that you set the 'Display material list' parameter in the planning variants. The spool list for the job then lists the planned materials.

Regards,
Srini

svs_sap
Active Contributor
0 Kudos
Former Member
0 Kudos

Ashutosh,

I suppose you must have overlooked the SCN rules of engagement.

http://scn.sap.com/docs/DOC-19331

where it is clearly stated that you should FIRST search for the answer on your own, before posting.

This question has been asked and answered dozens of times, example here.  There are many more, some of which have alternative answers.

http://scn.sap.com/thread/1482039

Best regards,