Skip to Content
author's profile photo Former Member
Former Member

Question regarding Delta

Hi Experts

I have one doubt

Suppose we are creating report using 2 infocubes say 0PUR_C01(uses data source 2lis_02_itm and 2lis_02_scl) and 0PUR_C04(uses datasource 2lis_02_hdr and 2lis_02_scl) .

Now my question is

Since both the cube uses the same datasource 2LIS_02_SCl and both are loaded with data for the first time using full load. Now when it comes to delta suppose the cube 0PUR_C01 is scheduled first and it takes the delta form the BW delta queue and now the delta queue is empty.

Now when it come to cube 0PUR_C04 there is no deltas in delta queue as the first cube successful delta load results in emptying the delta queue ??

Any replies would be greatly appreciated

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • Best Answer
    Posted on Jun 03, 2012 at 01:02 PM

    Hi,

    What suman speaks about fits for BW 3.X.

    In the case of 7X delta are target dependent and not on source dependent.

    3.X -- Delta is based on datasource

    7.X -- Delta is based on target(Because of the presence of the DTP)

    I hope you are using 7.X

    Regards,

    Lakshminarasimhan.N

    Add a comment
    10|10000 characters needed characters exceeded

    • Yes.

      You create transformations from the the datasource into each of your data targets (0PUR_C01 and 0PUR_C04). Then you create a DTP each, these will have to be set up with extraction mode DELTA.

      The delta status is managed on the level of each DTP individually.

      So to summarize you will have a DELTA Infopackage that delivers the data from your source system into BW. And then you have DTPs again with DELTA extraction mode to distribute the data further within BW into as many data targets as you like.

      Best,

      Ralf

  • Posted on Jun 03, 2012 at 12:15 PM

    Hi,

    In your Delta Infopackage -->Processing Tab-->PSA and then into Targets. -->Select both targets in Target Tab

    So Delta will get uploaded into both Cubes.

    Regards,

    Suman

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Suman

      Thanks for the reply

      But this option will be available only in 3.5 verison if I am not wrong. What about BI 7.x versions ? The option PSA and then to Targets and others except ONLY PSA are disabled so we cannot select this.

      Any other clue ?

      Regards.

  • Posted on Jun 04, 2012 at 02:43 AM

    In case of BI7

    with Infopacakge you can bring the data till PSA level only after that u need delta DTP so it will fetch or take the data to respective Infoprovider..

    so u need to have 2 DTP s for two Infoproviders.

    Thanks and regards

    Kiran

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jun 04, 2012 at 05:51 AM

    Hi all

    Thanks for you inputs

    Now its clear to me.

    Points assinged to all.

    Regards.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.