Source not included error in PO with outline agreement

Former Member
0 Kudos

Hello, I am facing below problem:

Source list maintain for RM1 material for plant 1 and vendor 1. source list and outline agreemnet both are valid till 31/12/2015.

if i create PO without outline agreeement reference, it works fine. if i create PO with outline agreement, it gives below error:

Source not included in list despite source list requirement

Message no. 06722

i have gone throgh below link and could not solve the error hence requesting to guide if there is any SPRO config/setting in mm01 releated to outline agreement and source list.

http://scn.sap.com/thread/1455993

Thanks in advance

Accepted Solutions (1)

Accepted Solutions (1)

JL23
Active Contributor
0 Kudos

have you entered the outline agreement as an item in your source list?

you need your vendor twice in the source list, once with outline agreement number, once without.

Former Member
0 Kudos

Thank  you very much Jurgen L.

Your quick response has helped me a lot!

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Check whether you have maintained the correct vendor/material/plant and validity dates in your source list.

I assume that you are trying to create PO with reference to Contracts (outline Agreement)

Thanks & Regards,

Former Member
0 Kudos

Thanks FC for your quick reply.

Everything works fine if i create PO without reference to Contracts (outline Agreement)

this error comes only when i create PO with reference to Contracts (outline Agreement)

prabhu_sundararaman2
Active Participant
0 Kudos

Hi,

Source list requirement has been set (mandatory) for your plant.

Therefore system is expecting source list for the vendor/material.

Ensure that the validity start and end date of contract matches with the validity start and end dates of the source list. If there is any mismatch, then you could get the error.

Regards