on 05-28-2012 10:46 AM
Dear All ,
we are working on strategy 40 . i have sales order of 10 Qty & in material master we have lot size procedure EX and the min lot size = 20 .
( as this part can be manufactured by us minimum 20 qty ) . By this the system is creating planned order with 20 qty .
Now this is with exception message 20 . But this is genuine , how to react or avoid this exception message ?>
Pl guide
Feed,
we are working on strategy 40 . i have sales order of 10 Qty & in material master we have lot size procedure EX and the min lot size = 20 .
( as this part can be manufactured by us minimum 20 qty ) . By this the system is creating planned order with 20 qty .
Now this is with exception message 20 . But this is genuine , how to react or avoid this exception message ?
Exception message 20 is 'Cancel', which means that the entire quantity of the planned order is excess. This is not consistent with the scenario you have mentioned above.
Normally, according to the scenario you described, MRP will generate a Planned Order of 20 qty with no message. The '20' exception message indicates that you have another element (stock? another Planned? Production? Purch Req? etc etc) that has already satisfied the 10 qty sales order requirement.
A common reason for such a '20' exception message is that multiple MRP runs have created multiple supply elements, some of which are firmed. I suggest that you review your rescheduling horizon settings.
http://help.sap.com/erp2005_ehp_06/helpdata/EN/f4/7d2c9744af11d182b40000e829fbfe/frameset.htm
Best Regards,
DB49
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks. This is good explanation.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
Please check the following wiki that I've created:
http://wiki.sdn.sap.com/wiki/x/xAJhE
It explains the rescheduling basics and there is an example where exception 20 is triggered because of the rescheduling settings.
BR
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Feed Mails wrote:
Dear All ,
we are working on strategy 40 . i have sales order of 10 Qty & in material master we have lot size procedure EX and the min lot size = 20 .
( as this part can be manufactured by us minimum 20 qty ) . By this the system is creating planned order with 20 qty .
Now this is with exception message 20 . But this is genuine , how to react or avoid this exception message ?>
Pl guide
I don't think that exception message 20 has any relavence with that Lot Size EX or Min Lot Size = 20. Please provide screen shot of MD04
Regards,
Dhaval
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Just leave blank in min lot size field...
If it is blank planned order will be created for only 10 qty instead of 20 qty (min lot size)
Or
one qn..
why you r requiring min lot size filed...
Check and revert back....
Regards,
PSM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.