Exception message 20

Former Member
0 Kudos

Dear All ,

we are working on strategy 40 . i have sales order of 10 Qty & in material master we have lot size procedure EX and the min lot size = 20 .

( as this part can be manufactured by us minimum 20 qty ) . By this the system is creating planned order with 20 qty .

Now this is with exception message 20 . But this is genuine , how to react or avoid this exception message ?>

Pl guide

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Feed,

we are working on strategy 40 . i have sales order of 10 Qty & in material master we have lot size procedure EX and the min lot size = 20 .

( as this part can be manufactured by us minimum 20 qty ) . By this the system is creating planned order with 20 qty .

Now this is with exception message 20 . But this is genuine , how to react or avoid this exception message ?

Exception message 20 is 'Cancel', which means that the entire quantity of the planned order is excess.  This is not consistent with the scenario you have mentioned above.

Normally, according to the scenario you described, MRP will generate a Planned Order of 20 qty with no message.  The '20' exception message indicates that you have another element (stock? another Planned? Production? Purch Req? etc etc) that has already satisfied the 10 qty sales order requirement.

A common reason for such a '20' exception message is that multiple MRP runs have created multiple supply elements, some of which are firmed.  I suggest that you review your rescheduling horizon settings.

http://help.sap.com/erp2005_ehp_06/helpdata/EN/f4/7d2c9744af11d182b40000e829fbfe/frameset.htm

Best Regards,

DB49

Answers (4)

Answers (4)

Former Member
0 Kudos

Thanks. This is good explanation.

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

Please check the following wiki that I've created:

http://wiki.sdn.sap.com/wiki/x/xAJhE

It explains the rescheduling basics and there is an example where exception 20 is triggered because of the rescheduling settings.

BR

Caetano

dhaval_choksi3
Active Contributor
0 Kudos

Feed Mails wrote:

Dear All ,

we are working on strategy 40 . i have sales order of 10 Qty & in material master we have lot size procedure EX and the min lot size = 20 .

( as this part can be manufactured by us minimum 20 qty ) . By this the system is creating planned order with 20 qty .

Now this is with exception message 20 . But this is genuine , how to react or avoid this exception message ?>

Pl guide

I don't think that exception message 20 has any relavence with that Lot Size EX or Min Lot Size = 20. Please provide screen shot of MD04

Regards,

Dhaval

Former Member
0 Kudos

Hi,

Just leave blank in min lot size field...

If it is blank planned order will be created for only 10 qty instead of 20 qty (min lot size)

Or

one qn..

why you r requiring min lot size filed...

Check and revert back....

Regards,

PSM

Former Member
0 Kudos

in other word consider this as my min Qty i have to produce . that we will produce but from system point of view its additional qty and will be treated as excess requirement for exception message 20 .

how to avoid this exception message in md04 ?

Former Member
0 Kudos

Hi,

instead of giving min lot size... maintain safety stock as 20 qty..

check and revert back...

Regards,

PSM