WPDTC report - planned delivery time in PO document

former_member207541
Contributor
0 Kudos

Hi,

Considering the PDT in PO document column of the WPDTC, why we have there always the PDT as in the info record and not the various PDT values derived from the delivery dates inserted manually in the purchase orders?

Thank you,

H.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Calculating the Planned Delivery Time   

Use

Use this function to calculate and change the planned delivery time. Using the documents in the system, the system calculates the number of days between the order being placed with the vendor and actual goods receipt. You can also use the planned delivery times calculated by the system in the master data as the planned delivery time.

By using this function you can achieve more efficient goods procurement from your vendor and therefore avoid overstock and out-of-stock situations.             

Scope of Functions

Until now, manual maintenance of data for the planned delivery time took place in three different places in the system:

at vendor level                                             

at material level                                               

at purchasing info record level.                                      

The values maintained manually here are, however, mostly based on past experience and can quickly become obsolete as the behavior of the vendor changes.

You use transaction WPTDC to call the function Calculate the Planned Delivery Time by workdays or calendar days and:

...

       1.      calculate the planned delivery time.                        

To calculate the planned delivery time, the system determines the number of days between the order being placed with the vendor and the actual goods receipt for a freely definable combination of vendor, plant, material, purchasing organization and vendor subrange.                                                          

       2.      change the date of the planned delivery time.

The function supports you in your decision of whether you want to keep the manually maintained planned delivery time or replace it with the calculated planned delivery time. You can decide this for each individual value in the master data for the vendor, material and purchasing info record.                   

Note that by changing the planned delivery time you can affect procurement.

Example

You notice that you have been getting increasingly more out-of-stock situations in your distribution center recently for a certain article from a vendor. You suspect that there is a discrepancy between the planned delivery time that has been entered in the system manually and the actual delivery time. Using the function for calculating the planned delivery time you can determine exactly how many days have passed between placing the order with your vendor and actual goods receipt. You compare the planned delivery time that has been entered manually with the planned delivery time calculated by the system. You establish that the vendor now requires three days longer to make the delivery that the date entered manually for the planned delivery time. You decide to copy the planned delivery time calculated by the system to the master data.