Issue with the Material BOM- change with a change number

former_member400804
Active Participant
0 Kudos

Hi,

We are facing a issue on changing a BOM using a change number. Consider Material "A" has BOM components as "C", "D", "E" AND "F" and while we try to change BOM without change number, all the components were in editable mode and in case we use change number with today or in future there are come components editable and some of them were not editable. (i.e., greyed out) . Do anyone facing similar issue,Lend me your thoughts to resolve this issue.

Thanks

Lenin. A

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello lenin,

Please review notes 1252123 on history changes. You will find information on how change numbers work. If you change an item with a change number , another item is created with it. You will not be able to change the same item anymore.

Thanks

Amber